Formation, Conseil, Coaching, Diagnostic,Optimisation des Couts,Organisation de la Qualité, Logistique de production, Industrialisation des produits, Optimisation des Délais, Démarche Lean manufacturing, Animation des KAIZEN, Optimisation de production, Optimisation des flux, Productivité, Ergonomie, Conditions de travail, Sécurité, Analyse du travail, Analyse fonctionnelle, Analyse de processus, Gestion des stocks, CMJ, consommation moyenne journaliere, Takt time, Lead time, Nomenclature, Gamme de fabrication, Planification, Planning de production, PERT, GANTT, Gestion de projet, Taux de Rendement Synthetique,TRS, Analyse de Processus, Définition des Procédés, Observations instantanées, Rendement des installations, Taux de service, Valeur ajoutée, Temps d’écoulement, Temps de cycle, Simogramme, Détermination des temps, Chronométrage, Jugement d'allure,Temps prédéterminés, MOST, MODAPTS, MTM, Analyse des modes de défaillance, AMDEC, Poka yoke, SMED, Single Minute Exchange of  Die, Changement de série, Organisation des approvisionnements, Etude de poste, Démarche 5S, Documents au poste, Kanban, Cahier des charges, Petit train d'approvisionnement, Equilibrage de ligne, Equilibrage de charge,Taux de saturation, Base de données, Chiffrage, Devis, Etude d'implantation, Gestion de Production Assistée par Ordinateur, GPAO, Ordre de fabrication, OF, MRP, Management de Ressources de Production, Maintenance des installations...

There are no translations available

 

Extrait de notre catalogue des formations en ligne.

Recevez notre catalogue des formations 2012 sur simple demande.(format papier ou PDF)

Read more...
 
There are no translations available

 

Vidéo Basic MOST® en ligne.

Visualisez notre vidéo de démonstration en ligne et appréciez la simpilicité d'utlisation du Basic MOST pour déterminer les temps de toutes vos activités.

Lire la suite...

 
English
Automated Mechanical Welding Unit PDF E-mail

 

Customer’s Demand

 - Decreasing times of cycles by a 15% on a mechanically-welded subgroup, initially realized in two phases: 

                               - Manual tack welding  

                               - Welding and robot-finition

 

- Integrating the business’ actors in the process to ensure a sustainable implementation.

   

 Key-Steps     

- Video-analysis and cycle timing

- Identification of potentials on background times

- Classification of potentials and ergonomic risks

- Research of solution in working groups

- Definition of a new operating process to be applied  

- Definition of the new adjustment and equipment

- SMED action

- Validation of technical solutions

- Implementation and training of operators

- Validation of results with a full-rate day

 

 Results 

 - Realisation of tack welding in background time during robot cycle, ie a 57% saving on cycle time, valued at 90K€/year.

- Production capacity allows saving of subcontracted pieces costs.

- Decrease of transit time by removal stock of outstanding discounted bills between the initial two working stations.

- Flexibility gains/savings with series-changing times lower than 3 minutes.

- Perfect integration of the process thanks to an active participation of the different actors.





Scooper cet article !Wikio !Taper cet article !Voter pour cet article !BlogMemes!Google!Facebook!Del.icio.us!
 
< Prev

Facebook Like

Automated Mechanical Welding Unit | Actions
COGITE NORD, formation Basic MOST, temps prédéterminés HB.MAYNARD, formation Basic MOST, temps prédéterminés
In partnership with COGITE NORD,  official Distibutor of H.B MAYNARD.

Formations les plus demandées

Derniers articles mis en ligne